Feasibility study for Designing of 65 km water pipeline

Project Information

  • Client:Best Way Cements
  • Location:Chakwal ,Punjab
  • Period:Feb-2018- Oct 2018

Project Overview

Design of Water Rising main and allied components for the supply of water from River Jhelum to Bestway Cement Plants located in Kahoon Valley Dist. Chakwal

Our Services

  • Design and specification of equipment and pipelines.
  • Preparation of detail drawing and BOQs.
  • Project documentation
  • Levelling and Mapping of the Project.
  • Electrical resistivity survey.
  • To study different pipe material for water pipelines and select most suitable material.
  • Carry out geotechnical investigations, excavation of shallow test pits, to evaluate geotechnical design parameters, condition along the route etc.
  • The Consultant will provide estimated quantity of Hard Rock Excavation and Soft Rock Excavation with maximum 10% variance.
  • Propose the electrical switch gears, starters, cables, power cables routes and control console for different pumping and booster stations including SCADA for control and monitoring. SCADA will include CCR, LCDs, Water Flow Displays, Power Failure Indications, Monitoring of Operator availability, Wireless Towers, SMS Scribtoins, Diesel Spillage/Monitoring and Security